Project Details
The Bunga Pakma (BP-A) is a minimum facility Wellhead Riser Platform. BP-A facilities will have 15 years design life. BP-A is located approximately 9 km from BO-A CPP. The current plan is to have BP-A facility operational First Gas-in by May, 2018. Production evacuation will be through a new export pipeline to BO-D I BO-A.
It’s envisaged that there will be six (6) new wells to be drilled in Y2018 on BP-A. Due to a change in tree allocation from the design stage, there is a requirement to re-route the HUC flowlines based on that latest tree allocation.