The task is to support Newfield’s existing project team undertaking the conceptual Study of PM329 East Piatu Development Project. The following scope of work are as follows :
- Preparation & drafting of basics process Flow Diagram (PFD) for 3 options of East Piatu Platform
- Assist in Larut process study & site visit
- Preparation of preliminary Platform layout & equipment sizing
- Preparation of preliminary Pipeline sizing
Client | : | NEWFIELD PENINSULA MALAYSIA INC |
Project Location | : | Block PM329 covers approx. 310 sq km in the Malay Basin and is located about 350 km offshore Kerteh, Terengganu. |
Project Duration | : | 5 weeks |
Weight | : | N/A |
Technical Description | : | N/A |
- Client NEWFIELD PENINSULA MALAYSIA INC
- Project Location 350 km offshore Kerteh, Terengganu
- Project Duration 5 weeks