Which is located approximately 148km offshore Bintulu at a water depth of 79 meters in block SK310. The first gas is expected in Q3 2008. Two (2) wells will be drilled, each is expected to produce up to 200 mmscfd. Gas production at plateau of 220 mmscfd is anticipated from PC4 field.

Gas production from PC4 will be tied back to B11 hub via a 12” pipeline for a distance of 25km. The gas will be metered prior to going into B11 processing facilities. B11 is jointly owned by (Sarawak Shell Berhad) SSB and PCSB with 50:50 ownership and operated by SSB.

PC4 field will be developed on a fast-track basis with the following facilities:

  • Unmanned minimum facilities platform with 2 single completion wells
  • Inter-platform Pipeline (about 25 km pipeline of size 12” to B11)
  • Host Tie-In activities at B11, E11 and BOCC
Client : PETRONAS CARIGALI SDN BHD
Project Location : Block SK310, Bintulu.
Scope of work undertaken by MMC O&G : FEED and Detailed Design.
Project Duration : 21 weeks
Weight :
Topside = 870mT
Flare Tower = 193mT
Jacket = 1160mT
Pile = 1430mT
Conductor = 390mT
Total weight = 4043mT
  • Client PETRONAS CARIGALI SDN BHD
  • Project Location Block SK310, Bintulu.
  • Project Duration 21 weeks